Dry-type transformers: copper cable and busbar on aluminium terminals
The low-voltage terminals of cast-resin (dry-type) transformers are often aluminium. Between a copper lug or copper busbar and an aluminium terminal goes a bimetal plate or washer, as the transformer makers' installation instructions require.
In short
The low-voltage terminals of cast-resin transformers are often aluminium. A copper lug or busbar on such a terminal needs a copper-aluminium bimetal plate or washer between them, aluminium face to the terminal. The SGB-SMIT and Hammond installation instructions both call for this. We supply the CUPAL® plate cut to the terminal's size and hole pattern.
- 0.5–2.0mm
- CUPAL sheet the plate is cut from
- M6–M20
- Washers, 11 sizes from stock
- 5–10working days
- Production of cut plates
- 24h
- Quote
Why an aluminium terminal needs a transition
Many makers of dry-type, cast-resin distribution transformers wind them in aluminium. A technical note on myelectrical.com states that Siemens GEAFOL transformers use aluminium for both the LV and the HV windings, and describes a site where copper cable was terminated on the transformer's aluminium terminals with bimetallic plates inserted between lug and terminal. The SGB-SMIT operating manual for cast-resin transformers also says the transformer's electrical terminals may be made of aluminium or of copper.
On the LV side the continuous current is high, the joint heats and cools with the transformer, and the substation is not opened for years. If a copper lug or copper busbar goes straight onto an aluminium terminal, an insulating oxide film grows on the aluminium, and wherever moisture is present the two metals form a galvanic cell. Bolt preload drops over the thermal cycles, contact resistance rises and the joint runs warm.
What the transformer makers specify
The makers' installation instructions agree: a bimetal transition goes between aluminium and copper.
| Maker, document | What it specifies |
|---|---|
| SGB-SMIT, Operating Manual for cast resin transformers (Rev. I, 20.02.2024), section 9.4 Phase terminals | Insert a copper-plated aluminium sheet between the copper/aluminium contact surfaces, with the copper-plated side against the copper terminal. Polish the contact surfaces metallically bright, again every time the contact is opened. On the aluminium side, add a washer to ISO 7093 in the threaded connection. |
| Hammond Power Solutions, ISOCAST cast-resin transformers, installation manual | LV connections are made with tinned copper lugs. For connection to the aluminium LV terminals through copper busbars, Hammond can provide Cupal plates or tinned LV terminals on request. |
| Hammond Power Solutions, VPI transformers, installation manual (German) | Connections between aluminium and copper busbars are to be made with CUPAL intermediate plates. |
| BTicino (Legrand), installation accessories for cast-resin transformers | 030009 "Piastrina CUPAL 60 x 60mm": a 60 × 60 mm bimetal plate, referencing CEI EN 60076-11. |
| Schneider Electric, TRIHAL FAQ | The neutral point is standardised as a copper bar with bimetal washers. The phase connector plates are tinned aluminium, so according to Schneider bimetal terminals are not necessary for connecting the power cables. |
In short, your transformer's own manual decides. Where it calls for a bimetal plate or washer, that is what we supply; where the maker says a tinned terminal needs none, you need none. We have no partnership with any of these manufacturers; we cite their documents as sources.
CUPAL is cold roll-bonded copper-aluminium bimetal, exactly the copper-clad aluminium sheet these instructions describe. We supply a CUPAL plate cut to fit the terminal from your drawing: to the terminal width, the hole pattern and the thickness you need. If a single bolt holds the joint, for example on the neutral bar, a CUPAL washer, M6–M20, is enough, with an outer diameter that covers the lug palm.
Which part for which terminal
The transformer's installation manual comes first. If it asks for a bimetal transition, this table helps you choose the form.
| Joint | Part | Note |
|---|---|---|
| Aluminium phase terminal → copper busbar | CUPAL plate cut to drawing | Cut to the terminal width and hole pattern, aluminium face to the terminal |
| Aluminium phase terminal → several copper cable lugs | Cut CUPAL plate covering all the lug palms | One plate, one contact face on the terminal |
| Neutral bar or a single-bolt joint | CUPAL washer M6–M20 | The outer diameter should cover the lug palm |
| Aluminium cable with a free end → copper terminal | Bimetal cable lug (ICALCU), 10–625 mm² | The transition sits in the lug body |
| Tinned aluminium terminal where the maker says no transition is needed | No CUPAL needed | Follow the transformer manual |
How the joint is built
Check the manual
Look up in the transformer's installation manual whether the terminal is aluminium or copper, and whether it calls for a bimetal interlayer.
Clean the faces
Polish the contact surfaces to bright metal just before assembly, and make sure no metal dust is left on the transformer. SGB-SMIT asks for this again every time the contact is opened.
Orient the plate
Aluminium face to the aluminium terminal, copper face to the copper lug or bar. The copper face is reddish, the aluminium face silver.
Assemble the bolted joint
In the SGB-SMIT drawing the joint consists of the bolt, a conical spring washer, an ISO 7093 washer on the aluminium side, the aluminium bar, the copper-clad aluminium sheet, the copper bar and the nut. Keep oil and general-purpose grease off the contact faces.
Tighten to the maker's torque
The torque comes from the transformer maker's table, by bolt size and bolt material. CUPAL has no torque table of its own.
What to send with your enquiry
- the terminal width and thickness, the hole diameter and spacing, or a dimensioned drawing (DXF, PDF, JPG);
- whether a copper busbar or cable lugs go on it, and how many lugs per terminal;
- the quantity per transformer and the number of transformers.
We quote within 24 hours. Plates take 5–10 working days in production, and EU door to door is 2–4 weeks; washers and bimetal lugs are stock items, 2–10 working days from order to delivery. Custom cutting has a minimum of one 500 × 500 mm sheet. A partner workshop does the cutting. Every shipment comes with an EN 10204 2.2 test report, and an EN 10204 3.1 inspection certificate on request.
Hammond rates its standard ISOCAST transformers for indoor installation in clean, dry rooms. If your substation is humid or outdoors, tell us: at the cut edge of the plate the Al/Cu bond line is exposed, and in that environment it needs protection too. If it is not the transformer terminal but the receiving switchboard where an aluminium bar meets a copper bar, joining aluminium and copper busbars is the closer page.
Questions from transformer installers
Applicable standards for this field
Knowledge base: CUPAL technical articles
4/10/2026
CUPAL bimetal installation and processing guide
Fitting a CUPAL bimetal washer step by step: surface prep, which face goes where, torque and edge protection outdoors. Plus the 260 °C / 4 h processing limit.
Read the full article →5/13/2026
EN 10204 2.2 certificate meaning: 2.2 vs 3.1
EN 10204 type 2.2 is a generic test report, type 3.1 a lot-specific inspection certificate. What each means, when you need which, and how to request one.
Read the full article →3/1/2026
Can copper and aluminium touch? Galvanic corrosion
They can touch, but where moisture reaches the joint the aluminium corrodes: 0.55 V apart in practice. What fails, and the bimetal washer that stops it.
Read the full article →